Keeping NEC records that will stand up when it matters

Which records to keep on an NEC job, who should own them, what makes a record usable as evidence, and the extra records cost-based options demand.

Communications and records3 min read

On this page
  1. Who should hold what
  2. Extra records on cost-based options
  3. What makes a record good evidence
  4. A quick illustration
  5. Habits that break records
  6. Related guides

Good NEC records let someone who was not there reconstruct what happened, who knew, what was said and what it cost, without relying on anyone's memory. You will rarely know in advance which record matters, so the aim is a habit that captures the basics every week, whatever the pressure.

Who should hold what

Contract administrator: every notice and reply, with the date sent and how it was delivered. This is how you show a notice went out or that an answer arrived late.

Planner: each programme revision as the native file and a PDF, with the reply that came back. Together they show what the Accepted Programme said on any given date.

Site manager and QS: the daily diary (what happened, and when you first knew), labour and plant allocation sheets, and weather readings taken at the place the Contract Data names.

Site team: photos and video that carry a date and a location.

Commercial team: delivery notes and purchase records, so you can say when materials arrived and what they cost.

Quality lead: test and inspection results, which cover quality, Defects and any delay caused by testing.

Each meeting chair: the notes of what was discussed and decided.

Register owner: the registers, with a dated copy saved every month.

Extra records on cost-based options

On Options C, D and E, which pay you your actual cost plus a fee, clause 52 lists records you must keep, including accounts of what you paid and how each figure was worked out. The Project Manager (the person the Client appoints to run the contract) can inspect them. Poor records cost real money here: Disallowed Cost includes cost your records do not support, so a gap can become a reduction in what you are paid. See Disallowed Cost and open book.

What makes a record good evidence

  • Made at the time. A note written the same day beats a polished statement written months later.
  • Specific. "Slow day" is weak. "Piling rig stood from 13:20 to 16:45, hydraulic fault, gang of four moved to steel fixing" is strong.
  • Attributable. It says who wrote it and when.
  • Linked. A photo with a date and grid reference tied to a compensation event number can be found in seconds.
  • Central. Project folders, not phones or personal drives.

A quick illustration

Imagine a dispute over a retaining wall. You say a late drawing delayed a pour by a week; the Project Manager says your rebar was late anyway. Five records settle it: the programme revision showing when the drawing was due, the communications log showing when it arrived, the delivery note and photo for the rebar, the allocation sheets and diary for that week, and the early warning register. With them, the argument ends in a meeting. Without them it may reach the dispute process.

Habits that break records

  1. Stopping when things get busy. The busiest weeks are often the ones you later need to prove.
  2. Recording only events you already know about. Keep a baseline, because you cannot photograph a site you have built over.
  3. Leaving key decisions in one person's inbox. Copy them to the project record.
  4. Editing registers in place. Save dated copies so history survives.
  5. Clearing out files at handover. Check how long your contract and your organisation need records kept, including any Scope requirement.

This guide is general information, not legal advice. Check it against your contract.