How the NEC fee percentage works, and what it has to cover

What the NEC fee percentage pays for, how NEC4 and NEC3 differ, where it applies by main Option, and a worked example of blending one percentage.

Payment and cost3 min read

On this page
  1. One percentage or two
  2. Where the Fee is used
  3. Blending: a worked example
  4. What the Fee actually contains
  5. What people get wrong
  6. Related guides

The fee percentage is the rate you tender to cover everything that Defined Cost does not pay for: typically head office overheads, profit, and any cost that has no home in the Schedule of Cost Components. Defined Cost is the contract's term for the actual cost you incur in providing the works, as the schedule allows. The Fee is the margin on top of it. In NEC4 ECC there is a single percentage (definition 11.2(10)); NEC3 ECC splits it in two (11.2(8)).

The figure goes in Contract Data part two, and under clause 52.1 the Fee is deemed to absorb every cost that is not Defined Cost.

One percentage or two

  • NEC4 ECC: one fee percentage, applied to all Defined Cost.
  • NEC3 ECC: a direct fee percentage, applied to work you do yourself, and a subcontracted fee percentage, applied to subcontracted work.

Under NEC4 you cannot price a lower return on subcontracted work separately. You have to blend. If you expect to subcontract most of the job, your single percentage must reflect that mix.

Where the Fee is used

  • Options A and B: only when pricing a compensation event from Defined Cost. Day-to-day payment comes from the Prices, which already hold your overhead and profit.
  • Options C and D: in each assessment, which is Defined Cost plus Fee, and also in the share calculation and when pricing events.
  • Options E and F: in every assessment and in the Prices.
  • Termination: in sums such as the fee percentage on the unworked balance, depending on the reason.

Blending: a worked example

Imagine a tenderer moving from NEC3 to NEC4, expecting £8m of Defined Cost on a bridge refurbishment. Under NEC3 habits it might price 10% on £2m of its own work and 3% on £6m of subcontracted work.

  • Own work: £2,000,000 at 10% gives £200,000.
  • Subcontracted: £6,000,000 at 3% gives £180,000.
  • Total Fee: £380,000 on £8,000,000.

That blends to 4.75% before allowing for anything that now has no component in the schedule. Every site running cost that has dropped out of the schedule adds to the figure. If the mix then shifts, say a large compensation event adds direct labour, you earn the same percentage on a different type of cost.

What the Fee actually contains

The contract does not list its contents. It is simply the home of whatever is excluded. A working checklist for an estimator:

  • head office and regional office overheads;
  • profit and a risk allowance;
  • people outside the Working Areas, apart from design or fabrication people priced at Contract Data rates;
  • tender costs, and ordinary business insurances outside the schedule;
  • in NEC4, site running costs with no listed component;
  • finance and other costs of doing business, unless a Z clause (an added condition) says otherwise.

Disallowed Cost comes out before the Fee is calculated, so the Fee can never pay for it. Lose £10,000 as disallowed and you lose the Fee on that £10,000 too.

What people get wrong

  • Calling it profit. A low percentage does not mean a low-margin bid until you know what the schedule leaves out.
  • Applying it to the wrong base. With deductions in an event, settle Defined Cost first, then add the percentage.
  • Expecting it to be reopened for a big change. It is a tendered figure used in every assessment, and moving it takes an agreement or a Z clause.
  • Expecting tender costs back. They were spent before the contract existed and fit no component.

This guide is general information, not legal advice. Check it against your contract.