Can you add head office overheads to an NEC price or compensation event?

Why head office overheads cannot be added as a separate line under NEC, how the Fee percentage covers them, and how to price a delay without losing money.

Payment and costScenario3 min read

On this page
  1. The short answer
  2. What to do, step by step
  3. What to record
  4. What not to do
  5. When to get help
  6. Example
  7. Related guides

You are pricing a delay or a change and your finance director wants a head office overhead line on top. Under NEC that line will almost certainly be struck out.

The short answer

Do not add a separate overhead line. NEC pays you for the cost of the work through Defined Cost (the cost items the contract allows you to charge, such as people, Equipment and Subcontractors), and then adds the Fee, a percentage you tendered. Clause 52.1 treats any cost that is not Defined Cost as already covered by that percentage. The Fee is therefore your whole recovery for head office, profit and anything else with no cost component. This holds on every main Option, including when you are pricing time-related costs. Only a Z clause (an additional condition written for the contract) can change it.

What to do, step by step

  1. List the genuine project costs the event caused: extra weeks of site staff, cabins, Equipment kept on, Subcontractor charges.
  2. Test each against the schedule of cost components in your contract. People only count as Defined Cost where the schedule says so, and that depends on where they work. The edges are set by the Working Areas (the places the contract defines as where you carry out the work) and anything wider that your Contract Data states.
  3. Leave out regional or head office rent, IT, finance and directors' time. These sit inside the Fee. Bid and tender costs usually do too.
  4. Add the Fee percentage to the total Defined Cost. In NEC4 ECC the percentage is entered in Contract Data at 11.2(10). NEC3 has two percentages, at 11.2(8).
  5. Check the Z clauses and Contract Data for anything extra that the contract expressly lets you charge.
  6. Submit your quotation within three weeks of the instruction to quote (62.3). If you are notifying the event yourself, remember the eight-week limit in 61.3.

What to record

  • Where each person worked and on which days, so you can show who falls inside the Working Areas.
  • Timesheets, hire invoices and Subcontractor valuations for the extended period.
  • The Fee percentage in your Contract Data, written on the quotation template so estimators see it.
  • Any Z clause or Contract Data entry that adds charges.

What not to do

  • Do not add a turnover-based overhead formula. Those belong to other forms of contract and have no place in an NEC assessment.
  • Do not argue that your real overheads were higher than the percentage. A tendered percentage is a tendered percentage, unless both sides agree rates or lump sums.
  • Do not bury a head office line inside another rate. If it is found, the Project Manager (the person who runs the contract for the Client) can remove it.
  • Do not treat a Client delay as a breach claim to get round the Fee. Breach by the Client is already a compensation event and is assessed the same way.

When to get help

Speak to your commercial manager before tender if the Fee looks too thin to carry your overheads, because it will under-recover on every event for the whole job. Take legal advice if a large sum depends on lost opportunities elsewhere, as NEC treats compensation events as your remedy for most of these. A planner can help you evidence the time-related costs.

Example

A fictional drainage subcontractor works on an Option A package with a 12% Fee. A compensation event holds up the crew for four weeks. Site team costs £40,000 and a pump and welfare unit cost £8,000, so Defined Cost is £48,000. The Fee adds £5,760, giving £53,760. The £22,000 the office manager wanted for central costs is not added, because the Fee is the only recovery for it.

This guide is general information, not legal advice. Check it against your contract.