A one-hour weekly routine for managing an NEC contract
A simple weekly hour that keeps NEC notices, replies, compensation events and the programme under control, with extra checks for each role.
On this page
Set aside one fixed hour a week for the contract. NEC is built on short deadlines, and most of the damage comes from a reply nobody noticed or an event nobody wrote down. A regular hour finds those while they are cheap to fix, and stops the paperwork turning into a monthly panic.
The routine below suits a mid-sized NEC4 Engineering and Construction Contract (ECC) job. Adjust it for other forms.
In plain English
Look back at what happened, check the clocks, push the stuck items, look ahead, and finish with three named actions. If the hour regularly overruns, your registers are not being kept daily, and that is the thing to fix.
The hour, in order
- Look back (10 minutes). Read the site diaries and progress notes since last week. Ask: did anything happen that is not yet on a register?
- Check the clocks (10 minutes). List every reply date falling in the next two weeks, plus anything overdue. Ask: what are we about to miss, and what has the other side already missed?
- Age your compensation events (15 minutes). A compensation event is a change or problem the contract says you are entitled to be paid or given time for. Sort the open ones by age and ask which is stuck and what would unstick it.
- Check the early warning actions (10 minutes). Has everyone done what they agreed to do?
- Look four weeks ahead (10 minutes). What access, information or Client-supplied items will you need soon?
- Set three actions (5 minutes). Names and dates, written down.
Extra questions by role
Your commercial lead
- Does any diary entry look like one of the events listed in clause 60.1? Note the day you became aware and notify comfortably inside the eight weeks in 61.3.
- Is a quotation falling due, and has your planner got the inputs?
- Is there a known problem that has not been the subject of a warning?
- Are you capturing costs now that you may have to justify later?
Your planner
- Is progress recorded finely enough to feed the next revised programme (32.1)?
- Will anything in the coming four weeks depend on the Client or on Others?
- When does the Contract Data interval make the next revision due?
On the Project Manager's side, ask yourself these in your head so you know what to expect: is a reply of theirs running late (a late reply can itself be a compensation event under 60.1(6)), and have they given an instruction that changes the Scope without a compensation event being notified (61.1)?
On the Supervisor's side: have all Defects found this week been notified (43.2), and are tests booked so they do not hold up work (41.5)?
A worked week
A pumping station refurbishment on Option C. On Monday the site manager's diary shows that on Friday the crew dug up a land drain that is not on any drawing and cut a trench around it. Nobody mentioned it again. In her hour, the commercial manager:
- Records Friday as the day of awareness, with the diary reference.
- Asks for a photograph and a two-line note of what was done.
- Issues an early warning, because extra cost or delay is possible.
- Decides whether it fits 60.1(12), and notifies it that week if so.
- Puts it on the agenda for the Wednesday meeting.
Five minutes on a Monday. Left until the end of the job, with the crew gone, it could take weeks to reconstruct.
What to do with what you find
- You are late: answer now anyway and record the reason. If you still have time on the clock but need longer, ask for an extension before it runs out (13.5).
- They are late: a polite reminder comes first. If that fails, use the formal route for that kind of communication. See tracking periods for reply.
- A compensation event is stuck: identify the one blocker. A quick conversation between two people often moves it faster than more letters.
Keep the slot fixed, and brief a deputy with the same list so the hour survives holidays and sickness, which is when deadlines usually slip. Feed the month's findings into your contract report.
Related guides
- Registers every NEC contract needs
- Compensation event notification checklist
- Running an early warning meeting
- Time limits across the contract
This guide is general information, not legal advice. Check it against your contract.