Ending an NEC subcontract: how it links to the main contract
How termination works in an NEC subcontract: the R23 reason when the main contract ends, shorter periods, and what each party should check.
On this page
Ending an NEC subcontract follows the same pattern as the main contract, except that the main contractor does the Project Manager's job and issues the certificate. The big addition in the NEC4 Engineering and Construction Subcontract is reason R23 (clause 91.9): the main contractor may terminate because its own main contract has been terminated. The two contracts are linked, but they do not end automatically together, and you need to manage that gap.
In plain English
If the main contract falls, the subcontract does not fall with it. Someone has to decide whether it passes to the Client, ends, or pauses, and that decision costs money.
The NEC4 subcontract table
- Main contractor ends it for R1 to R15, R18 or R22: procedures P1, P2, P3, with amounts A1 and A3.
- Main contractor ends it for R17, R20 or R21: P1 and P4, with A1 and A2.
- Main contractor ends it because the main contract ended (R23): P4 only, with A1, A2 and A4.
- You end it for R1 to R10, R16 or R19: P1 and P4, with A1, A2 and A4.
- You end it for R17 or R20: P1 and P4, with A1 and A2.
R23 can be costly for the main contractor. A4 gives you a fee on the unfinished subcontract work however the main contract came to an end, including through the main contractor's own default.
How the subcontract differs from the main contract
- Certificate: the main contractor issues it.
- Time to put a default right: 3 weeks in the NEC4 subcontract, against 4 weeks in the NEC3 and NEC4 ECC and 3 in the NEC3 subcontract.
- Non-payment (R16): 13 weeks.
- Long stop-work reasons (R18 to R20): 14 weeks.
- Terminating for any reason: in NEC4 the main contractor needs Option X11 for this, with P1, P2 and A1, A2, A4. The NEC3 subcontract has an any-reason row built in.
- R23: exists in NEC4 only.
On an NEC3 subcontract, a main contractor whose own contract has ended usually relies on the any-reason row. Amended forms need checking.
Three possible fates when the main contract ends
Under the main contract, procedure P2 can make the main contractor hand the benefit of its subcontracts to the Client. That leaves three outcomes for you as subcontractor:
- Transfer. The Client or a replacement contractor takes over the benefit and you carry on.
- Termination. The main contractor ends the subcontract under R23 (or the NEC3 any-reason row) and pays the amounts due.
- Pause. You are told to stop while others decide. A stop instruction can lead to reason R20 once the stated period has run.
If you are told to continue for a new party, get it in writing, including who pays for work already done and work still to come.
Example
Take a fictional ventilation subcontract valued at £1 million, of which £400,000 is finished, with a 12% fee percentage. The Client ends the main contract and decides not to adopt the subcontract.
- The main contractor gives notice under R23 and certifies.
- You take your Equipment out and leave the Working Areas (P4).
- The fee under A4 is 12% of the £600,000 not yet done: £72,000, added to A1 and A2.
- A main contractor terminated for its own default should assume that bill is its own.
Keeping the two contracts in step
- Periods: a subcontract default may need resolving faster than the main contract allows. See back-to-back subcontracts.
- Disputes: W1 and W2 in the subcontract include rules for joining a subcontract dispute to a main contract adjudication. Under W2 consent is needed.
- Assignment: make sure the subcontract lets the benefit pass to the Client, or P2 will not work.
- Non-NEC subcontracts: the acceptance process in clause 26 of the main contract still applies, and you must read the other form's termination rights closely.
- Insurance and bonds: check how they respond at termination and who benefits.
For subcontractors
Check the fee percentage and any Z clause that deletes A4 before you sign. Keep a running record of committed cost, since other Defined Cost reasonably incurred can turn out to be a large item at the end. If your main contractor is in trouble, read insolvency and NEC contracts and get advice before leaving site. Your rights against the main contractor are separate from any direct arrangement with the Client. For more background see NEC subcontracts explained.
Related guides
- Termination under NEC
- Insolvency and NEC contracts
- NEC subcontracts explained
- Time bars for subcontractors
This guide is general information, not legal advice. Check it against your contract.