What happens to an NEC contract when the other side goes insolvent

How NEC treats insolvency (reasons R1 to R10), what you are paid, the legal limit on suppliers terminating, and how to protect yourself before trouble starts.

Disputes and termination4 min read

On this page
  1. In plain English
  2. The listed events
  3. Who is affected, and how
  4. The legal limit on suppliers
  5. Protection to arrange before it happens
  6. Warning signs
  7. Example: a Client's view
  8. If the failure is lower down the chain
  9. Related guides

If the other party hits one of the insolvency events listed in the contract, reasons R1 to R10 may let you terminate. Whether you actually can, and whether you should, depends on which side has failed and on UK insolvency law. The relevant clause is 91.1 in both NEC3 and NEC4. Insolvency is a strict legal area, so use this as background and get advice before acting.

In plain English

The contract lists the events. The law then limits what a supplier may do in response. A contractor is normally a supplier to its Client, so you should not assume the list gives you a free exit.

The listed events

  • An individual: a bankruptcy application (NEC3: petition), a bankruptcy order, a receiver over assets, or an arrangement with creditors (R1 to R4).
  • A company or partnership: a winding-up order, a provisional liquidator, a winding-up resolution (other than to merge or reconstruct), administration, a receiver over all or most of the business, or an arrangement with creditors (R5 to R10).

Who is affected, and how

Contractor fails Client fails
Who may terminate The Client The Contractor, subject to the legal limit below
Procedures P1, P2, P3 P1, P4
Amounts A1, A3 A1, A2, A4
In practice The Client tries to finish the job and recover the extra cost You are likely an unsecured creditor for much of what you are owed

Section 233B of the Insolvency Act 1986, brought in by the Corporate Insolvency and Governance Act 2020, stops a supplier terminating, or doing certain other things, merely because the customer has gone into a covered insolvency procedure. Exceptions exist, and there is a way to ask the court for permission.

Because a main contractor supplies the Client, you cannot assume R1 to R10 is usable against a Client in that position, even though the contract appears to permit it. The same reasoning applies between a main contractor and its subcontractors. A Client ending a failed contractor is on different ground, being the customer. If you are unpaid, R16 (non-payment) or suspending work under the Construction Act may be open to you, but the restriction also catches some conditions that arose before the insolvency, so each route needs advice.

Protection to arrange before it happens

Protection What it gives you
Parent company guarantee (Option X4) Another company stands behind the Contractor
Performance bond (Option X13) A third party pays up to a stated sum
Retention (Option X16) The Client holds back a percentage
Project Bank Account (Y(UK)1) Payments go through a dedicated account
Marking Plant and Materials (clauses 70 and 71) Ownership of goods held off site, so far as the Contractor has it
Advance payment (Option X14) Secure it with a bond if the contract requires one

Warning signs

  • Subcontractors grumbling about late payment, or walking off.
  • Deliveries slipping, with suppliers demanding tougher terms.
  • Applications that ask for more than the work done.
  • Senior people leaving, or the site suddenly quiet.
  • Odd requests: money paid early, or new bank details.

These are good grounds for an early warning (a notice that flags something which could affect cost, time or quality). See what should be an early warning.

Example: a Client's view

A fictional Client has a clinic project 60% built under Option A when its Contractor enters administration. Sensible steps:

  1. Do not rush. The administrator may want to finish the job, so talk to them.
  2. Secure the Site and protect the work, with their cooperation.
  3. If advised, serve notice under R8 and have the Project Manager certify.
  4. Use P2 and P3 only as far as practical, checking who owns what, since unpaid suppliers may claim goods.
  5. Call on any bond or guarantee strictly to its terms and deadlines.
  6. Record the extra cost carefully for A3. Insolvency rules on set-off may affect the final account.

If the failure is lower down the chain

When your own subcontractor fails, the main contract does not change. You still have to Provide the Works, and there is generally no compensation event. See ending an NEC subcontract.

This guide is general information, not legal advice. Check it against your contract.