Can you walk away from an NEC contract? The contractor's termination rights

The few reasons that let a contractor end an NEC contract, the waiting periods, what you are paid, and the steps and risks to weigh before serving notice.

Disputes and terminationScenario4 min read

On this page
  1. The short answer
  2. What to do, step by step
  3. A warning on insolvency
  4. What to record
  5. What not to do
  6. When to get help
  7. Example
  8. Related guides

The Client is not paying, or has frozen your job, and you are asking whether you can just end the contract. Under NEC the answer depends on the Termination Table: you need a listed reason, and bad decisions or a soured relationship are not listed.

The short answer

Yes, but only on one of four grounds: the Client's insolvency, prolonged non-payment, a prolonged stop instruction, or a legal release from the contract. Slow replies and poor decisions are dealt with through compensation events and disputes. Whichever ground you can prove sets your payment, so test it before drafting any notice.

What to do, step by step

  1. Test the reason. Take non-payment (R16): is the sum really due? If the Project Manager (the person the Client appoints to run the contract day to day) never certified it, expect an argument. Pin down the position in writing first.
  2. Fix the start of the count. It begins when payment fell due or the instruction was given, never on the day you first complained.
  3. Consider suspending first. The Construction Act lets an unpaid party stop work after giving notice, and where Y(UK)2 applies that is a compensation event (Y2.5 in NEC4, Y2.4 in NEC3). It can be reversed; termination cannot.
  4. Price the exit. Put A1, A2 and any A4 beside what you would earn by finishing. Done honestly, the sums often favour staying.
  5. Take legal advice. If you terminate wrongly, that is your breach, and the Client may say you abandoned the job.
  6. Notify the Client and the Project Manager, stating the reason (clause 90.1).
  7. Wait for the certificate. The Project Manager issues it promptly if the reason complies, and the procedures begin after that. On every reason below you then leave the Working Areas and take your Equipment (P1 and P4).

The reasons open to you:

  • R1 to R10, insolvency of the Client (clause 91.1): no waiting period, but see the warning below. You recover A1, A2 and A4.
  • R16, non-payment (91.4): a sum due stays unpaid for 11 weeks in NEC3 ECC or 13 weeks in NEC4 ECC. You recover A1, A2 and A4.
  • R17, legal release (91.5): the law has freed both sides from the whole contract. A1 and A2.
  • R19, stop caused by the Client (91.6): 13 weeks with no restart in both ECC editions. A1, A2 and A4.
  • R20, stop for any other reason, not your default (91.6): same 13 weeks. A1 and A2.

The NEC4 subcontract has its own periods: 13 weeks for R16 and 14 for R19 and R20. Amended contracts differ, so read your own clause 91.

A warning on insolvency

On paper the contract allows termination when the Client becomes insolvent. In law, section 233B of the Insolvency Act 1986 curbs a supplier's right to end a contract on that ground, and you are usually the supplier. Read insolvency and NEC contracts and take advice first.

What to record

  • The certified amount, the date it was due and the date it should have been paid.
  • Any pay less notice, or the absence of one.
  • Suspension notices and the Client's responses.
  • Adjudication decisions and whether they were honoured.
  • The stop instruction, if relying on R19 or R20, with dates and reasons.

What not to do

  • Do not leave site because you have complained. The procedures start only after the certificate.
  • Do not count from the wrong date.
  • Do not skip the cheaper step of suspension without thinking it through.
  • Do not terminate for a reason that does not fit your facts.

When to get help

Involve a lawyer before serving any notice, and your commercial manager before you price the exit. If the Project Manager is slow or refuses to certify, do not just go. An Adjudicator can review the Project Manager's inaction, and adjudicate or negotiate covers timing. Expect the Client to pay at the last minute, which removes the reason, to say the sum was not due, or to claim a right to set off. A counter-allegation of your own default needs its own test.

Example

A fictional NEC3 groundworks contractor is owed £150,000 on a certificate due for payment on 1 March, and no pay less notice was served. Eleven weeks later, in mid-May, it has suspended work, won an adjudication the Client ignored, and now takes advice. It notifies R16 and requests the termination certificate. Under NEC4 ECC it would have had to wait 13 weeks. All figures are invented.

This guide is general information, not legal advice. Check it against your contract.