Preparing an NEC compensation event quotation that gets accepted

What goes into a compensation event quotation, how to handle the programme and alternatives, and the mistakes that get quotations sent back.

Compensation events and change3 min read

On this page
  1. In plain English
  2. What the quotation must contain
  3. Handling the programme
  4. Offering alternatives
  5. Mistakes that get quotations returned
  6. Quotations for proposed instructions
  7. Related guides

A compensation event is something the Client carries the risk for, so your price and dates get reassessed. The quotation is your written proposal for how far they should move. Despite the name, it is not a tender. It is an assessment that must follow the rules in clause 63, and you have three weeks from the instruction to quote to send it (clause 62.3).

In plain English

Show your workings. The Project Manager, the person the Client appoints to run the contract day to day, will accept a quotation they can check and return one they cannot.

What the quotation must contain

Think of it as a pack with eight parts:

  1. Reference. Which event, which notice, which instruction to quote.
  2. Price change. A total made of cost already incurred, cost still forecast, and the Fee, laid out the way your main Option requires.
  3. Time. The move in the Completion Date and in each Key Date affected, or a plain statement that nothing moves.
  4. Back-up. People, Equipment, Plant, Materials, subcontractors and other charges, with quantities and rates.
  5. Risk allowances. What each one covers, how likely the risk is and how you arrived at the figure.
  6. Programme. Changes to the Accepted Programme, or a marked-up extract that shows the critical path.
  7. Assumptions. Anything the Project Manager stated under 61.6, taken exactly as stated.
  8. Dividing date. The cut-off between actual and forecast, and how the effect is measured from it.

The cost headings come from the Schedule of Cost Components. In NEC4 you can also agree rates or lump sums with the Project Manager (63.2).

Handling the programme

If the event changes how the rest of the job runs, show it. A complete replacement programme every time is not required, but the sequence before and after must be clear enough for the delay to be checked.

  • Begin with the Accepted Programme that stood on the dividing date.
  • If a required programme has not been submitted, or the latest was turned down on a ground the contract allows, the Project Manager may carry out the assessment instead under clause 64. Programme gaps can sink a sound quotation. See when the Project Manager assesses.

Offering alternatives

Clause 62.1 lets the Project Manager request alternative quotations after discussing practical options with you. Imagine a Client's pump set arrives six weeks late on a pumping-station refurbishment:

Option Idea Price Delay
A Wait and keep the sequence +£85,000 6 weeks
B Resequence using a second crew +£120,000 2 weeks
C Your proposal: hire a temporary pump +£150,000 none

The Client then chooses what fits its priorities. This is one of the most helpful features of the clause and one of the least used.

Mistakes that get quotations returned

  • Pricing at tender rates. Unless agreed otherwise, you price Defined Cost plus Fee, not bill rates.
  • A single lump sum. With no breakdown, the Project Manager can reject it or assess the event themselves.
  • Piling on contingency. Risk allowances are for risks with a real chance of occurring (63.8 in NEC4), each explained, not a general cushion.
  • Folding in other events. Notify and assess those separately.
  • Waiting for actual cost. The contract expects a forecast for work still to come, assuming you respond promptly and sensibly (63.9 in NEC4).
  • Skipping a 61.5 statement. If the Project Manager says you should have warned, answer it.

Quotations for proposed instructions

Sometimes the Project Manager wants a price before they decide to instruct. In NEC4 this is clause 65: they name a date by which they might instruct, and you must not act unless they do. If they turn the quotation down, 60.1(20) makes that a compensation event so your pricing cost is recoverable. NEC3 handles this in 61.2 and 62.3.

This guide is general information, not legal advice. Check it against your contract.