NEC Option X1 price adjustment: how inflation is paid on your contract

How X1 moves your prices with published indices on Options A to D, with a worked calculation and the traps around compensation events.

NEC Options and contract types3 min read

On this page
  1. Is it worth having?
  2. How the figure is built
  3. A worked example
  4. NEC3 against NEC4
  5. What goes wrong
  6. Related guides

With Option X1 the Prices rise and fall with published cost indices, so after the base date (the date from which price movements count) inflation is the Client's problem and not something you have to guess at tender. It is available only on main Options A to D, and acts differently on the fixed-price options and the target ones. It is not part of your contract unless the Contract Data selects it. The clause numbers here are for the NEC4 ECC unless stated.

Is it worth having?

Long jobs, and jobs exposed to swings in materials or labour, are where X1 earns its keep, because a fixed allowance there is a gamble. On a short job priced by quotation it may mean effort for little return. Option E has no X1 since the Client already pays actual cost, and Option F does not offer it either.

The trade is simple. With X1 you leave long-range inflation out of your price and the Client lives with an uncertain final bill. Without X1 you either price the risk or swallow it.

How the figure is built

The Contract Data lists the share of the work tied to each named index and the base date. At each assessment you work out the Price Adjustment Factor (PAF):

  1. For each index, compare the latest published figure against the one from just before the base date.
  2. Turn that into a percentage change.
  3. Multiply by that index's proportion.
  4. Add the results for all indices. The total is the PAF.

What the PAF then does depends on the main Option.

Main Option Effect NEC4 NEC3
A and B An adjustment amount is added on top of each amount due X1.3 X1.4
C and D The total of the Prices is increased, so the target shifts and you feel it through your share X1.4 X1.5
Compensation events Defined Cost is held at base date levels, to avoid paying inflation twice X1.5 (subcontract text) X1.3

Because the numbers moved between editions, check every X1 reference when you carry a template from NEC3 to NEC4.

A worked example

On an invented culvert scheme, 70% of the cost mix is tied to a labour index and 30% to an aggregates index.

  • Labour moves from 100 to 105: change 0.05, times 0.7 gives 0.035.
  • Aggregates move from 150 to 162: change 0.08, times 0.3 gives 0.024.
  • PAF = 0.059.

Suppose the Price for Work Done to Date has risen £400,000 since the last assessment.

  • Option A: new adjustment is £400,000 x 0.059 = £23,600, added to the adjustment from earlier assessments.
  • Option C: the target moves up by £400,000 x (0.059 / 1.059), about £22,285. The divisor appears because the figure is built from Defined Cost, which is already at today's prices.

NEC3 against NEC4

  • If an index is corrected: NEC3 has you redo the sum and add a correction, whereas the NEC4 subcontract text leaves an earlier calculation closed.
  • Late in the job: NEC3 fixes the factor at the Completion Date of the whole works. The NEC4 subcontract text takes the final assessment ahead of that date.
  • Compensation events: the NEC4 subcontract text uses the dividing date when stripping current cost back to base levels.

I have taken these three points from the subcontract wording, so confirm each against your own NEC4 ECC.

What goes wrong

  • Counting inflation twice in a compensation event: price at current rates, then let X1 inflate it again. Bring the cost back to base date levels first.
  • Loose index entries. Name the publisher, the series and the reference in the Contract Data.
  • Proportions that do not match the real cost mix. They are fixed at tender, so test them.
  • Looking for the money on Option C. It is not a payment line. It moves the target, and you see it only through your share.

This guide is general information, not legal advice. Check it against your contract.