NEC Option Y(UK)2: how it sets your payment dates and pay less rules

What Option Y(UK)2 does for payment timing, pay less notices and suspension, with a dated example and the NEC3 versus NEC4 numbering.

NEC Options and contract types3 min read

On this page
  1. What it covers
  2. The periods
  3. A dated example
  4. Why it matters to you
  5. Common slips
  6. Related guides

Option Y(UK)2 is the part of an NEC contract that builds the UK Construction Act's payment rules into the conditions. In practical terms it fixes the due date and the final date for payment, makes the certificate act as the payment notice, and sets how the Client (or you) may pay less than the notified sum. Where the Act applies but the Option is absent, the contract's payment terms may fall short of the law, and the statutory Scheme can step in to fill the gaps. It takes account of the 2009 changes to the Act. If you are unsure the Act applies to your project, take advice.

What it covers

Subject Effect NEC4 clause NEC3 clause
Counting days Christmas Day, Good Friday and bank holidays are left out, as in the Act Y2.1 (subcontract text) Y2.1
Payment dates Fixes the due date and final date, and gives the certificate its job Y2.2 Y2.2
Paying less Notice is needed no later than a week before the final date Y2.3 Y2.3
Suspension A suspension permitted by the Act is a compensation event Y2.5 Y2.4

Suspension is where numbering trips people: Y2.4 became Y2.5 in the NEC4 ECC, PSC and PSS, while the NEC4 ECS text prints Y2.4 against both suspension and its termination rule. In the NEC4 PSC, PSS and subcontract wording, one more clause deals with a certified sum left unpaid when the contract ends for certain listed reasons.

The periods

In the NEC3 ECC, payment falls due seven days after the assessment date, and the final date for payment is two weeks later unless the Contract Data says otherwise. The NEC4 subcontract text uses fourteen days to the due date. Forms and versions differ, so check the wording in your own copy and do not rely on memory.

A dated example

An invented NEC3 ECC job, with no change to the final-date period and no bank holidays in the way.

  • Assessment date: 3 February.
  • Payment due: 10 February.
  • Last day for a pay less notice: 17 February.
  • Final date for payment: 24 February.

The certificate says £120,000 is due to you. The Client wants to take off £15,000 for something it says you owe. If it sends a proper pay less notice on 16 February, stating £105,000 and how that was worked out, it can pay £105,000 by 24 February. If the notice goes out on 18 February, it is late, and the full £120,000 stays payable.

Figure 1. The dated NEC3 ECC example. The assessment date of 3 February is day 0, payment falls due on 10 February (day 7), the last day for a pay less notice is 17 February (day 14) and the final date for payment is 24 February (day 21). A notice on 16 February stating £105,000 is valid, so the Client may pay £105,000. A notice on 18 February is late and the full £120,000 certified stays payable.
Figure 1. The dated NEC3 ECC example. The assessment date of 3 February is day 0, payment falls due on 10 February (day 7), the last day for a pay less notice is 17 February (day 14) and the final date for payment is 24 February (day 21). A notice on 16 February stating £105,000 is valid, so the Client may pay £105,000. A notice on 18 February is late and the full £120,000 certified stays payable. Open full size

Why it matters to you

  • The certificate has legal weight. It is the payment notice and states the notified sum, so a late or careless one is more than an admin slip.
  • Either side can give a pay less notice, including where you owe the Client money.
  • Deductions need a notice. Saying so in a meeting is not enough.
  • Suspension is protected. If you suspend properly for non-payment, the effect on you is a compensation event. A wrongful suspension can be serious, so take advice first.

Common slips

  1. Counting calendar weeks. Day periods skip certain holidays, so dates around Christmas and Easter come out wrong.
  2. Quoting NEC3 numbers in NEC4 letters, especially Y2.4 for suspension.
  3. Assuming a Z clause can rewrite everything. The Act sets minimum rules, so unusual payment schedules need a legal check.
  4. Forgetting adjudication. The Act gives a right to adjudicate at any time, which is why Option W2 normally goes with Y(UK)2.

This guide is general information, not legal advice. Check it against your contract.

Was this useful?