The Project Manager has told you to stop work: what next?

Obey the instruction, then protect your position. How an NEC stop work instruction becomes a compensation event, and when your own fault removes it.

Compensation events and changeScenario3 min read

On this page
  1. The short answer
  2. What to do, step by step
  3. What to record
  4. What not to do
  5. When to get help
  6. Example
  7. Related guides

The Project Manager (the person the Client appoints to run the contract day to day) has told you to stop. You have to comply, and what you do in the next few days decides how well you are paid for it.

The short answer

Stop, make the work safe, and confirm in writing. An instruction to stop or not start work under clause 34.1 must be followed, and it is normally a compensation event under clause 60.1(4), unless it arises from your own fault. The clause numbers match in NEC3 and NEC4. Under the NEC4 subcontract the instruction comes from the Contractor.

What to do, step by step

Today

  1. Check who gave it. Only the Project Manager, or someone they have formally notified as their delegate, can instruct you. A request from the Client's own staff is a separate issue to raise.
  2. Get it in writing if it was spoken.
  3. Pin down the extent: which work, which area, from when, and whether it covers off-site fabrication and design.
  4. Make the work safe, and ask whether anything must carry on for that purpose.
  5. Tell your subcontractors and suppliers promptly, under their own contracts.
  6. Record what is on site when the stop begins: people, plant, materials, hire and orders.

This week

  1. Check the Project Manager has notified the event (clause 61.1) and asked for quotations (clause 61.2). If not, notify it yourself under clause 61.3. An event that stems from an instruction escapes the eight-week limit, but delay gains you nothing.
  2. Ask how long it will last. If nobody knows, the Project Manager can state assumptions for the quotation (clause 61.6), corrected later.
  3. Quote within three weeks of being told to, covering standing costs, demobilisation, remobilisation and the effect on later work.
  4. Cut the cost where reasonable: off-hire plant, redeploy gangs, and tell the Project Manager what you did.

What to record

  • The instruction, its stated reason and its time
  • Resources standing each day, with hire records
  • Subcontractor and supplier notices
  • Redeployment and mitigation steps
  • A weekly cost summary you can hand to the Project Manager

What not to do

  • Do not carry on working while you argue.
  • Do not record resources once and never update them. Standing cost changes week by week.
  • Do not accept a vague instruction. Ask for the reason in writing.
  • Do not mix reasons. If part of the stop is your fault, such as an unsafe scaffold, and part is the Client's wish to pause, keep the two periods apart.

If the stop arises from your fault, no quotations are requested (clause 61.2) and the Prices and dates do not change (clause 61.4).

When to get help

Get a commercial manager involved immediately if the reason is unclear or disputed. Ask a planner to model restart options. A long suspension of substantial work can open the door to termination after a set period, which is a legal matter.

At the end, NEC4 has the Project Manager instruct a restart or a start, or take the work out of the Scope (which also engages clause 60.1(1)). NEC3 only provides for restarting.

Example

A rail possession job on Option A stops when the Client's funding review begins. The crew is told to down tools on a Friday afternoon. By Monday you have sent a short email that says which clause the instruction came under, what you stopped and when, how far you understand it reaches, and the reason given. It states that you do not see it as your fault, asks the Project Manager to notify a compensation event and to say how long the stop will last (or give assumptions), asks whether any protective work is needed, and promises weekly resource records. That one email covers most of what you will later need to show.

This guide is general information, not legal advice. Check it against your contract.