Cannot price the quotation yet: assumptions and risk allowances
When facts are unknown, ask the Project Manager for assumptions or price the risk, but never let the quotation deadline pass without submitting.
On this page
A compensation event has landed and you cannot say what it will cost, because a key fact is still unknown. The quotation clock is running regardless.
The short answer
Start by asking why the price is out of reach. Where the effects genuinely cannot be forecast, request assumptions from the Project Manager under clause 61.6 and price on those. Where the unknowns are everyday risks with a real chance of happening, build a risk allowance into the quotation under clause 63.8. Either way, do not wait. A missed quotation date lets the Project Manager make its own assessment under 64.1, and NEC expects a quotation to be a forecast.
What to do, step by step
- Write down the unknowns and pick out the ones that really change the figure.
- Request an assumption in writing straight away. They normally come with the instruction to quote, so if none did, ask and offer draft wording.
- Ask for more time before the deadline if you need it. Under clause 62.5, an extension works only if both sides agree before the submission is due.
- Submit on time anyway. A quotation listing its assumed basis and allowances beats none. The period is three weeks in the ECC (62.3) and two in the NEC4 subcontract.
- Keep the workings. Show for each allowance the chance, the consequence and its purpose.
Sort the unknowns
| Your unknown | Route |
|---|---|
| A large fact nobody can yet estimate | Assumption (61.6) |
| A Client decision still to come | Assumption, or ask for the decision |
| A risk with a real chance of happening that is not itself an event | Risk allowance (63.8) |
| A remote risk that would be an event if it happened | Leave out, notify if it happens |
| A price you have not yet obtained | Chase the supplier, or request more time |
NEC3 numbers the risk allowance rule 63.6. The assumption rule is 61.6 in both. A later correction is itself an event under 60.1(17), which lets the figure follow the facts in either direction. Without an assumption, you bear the risk of being wrong, because an assessment is not later revised just because a forecast was wrong.
A sample request, invented: "We cannot sensibly forecast CE-088 until the ground investigation reports on 19 June, and our quotation is due 12 June. Please state under clause 61.6 the assumption we should price. We suggest that the contaminated area does not exceed 120 square metres and that treatment is limited to excavation and disposal."
What to record
- The unknowns and why they cannot yet be priced.
- Your written request for an assumption and any reply.
- Supplier enquiries.
- The build-up of each allowance.
What not to do
- Do not wait and hope to be paid actuals. NEC does not provide that by itself. If both sides really want it, record an agreed approach in writing, or agree rates or lump sums under clause 63.2.
- Do not use a vague contingency percentage. It invites the label "padding".
- Do not assume the Project Manager must give an assumption. The decision is its, so be ready to price the risk honestly.
- Do not treat the Project Manager's own assessment as your failure. It is not, and you can dispute it.
When to get help
Half an hour with the Project Manager before you quote, settling which unknowns get assumptions, can spare weeks of revisions. Bring in a commercial manager to build the allowances and a planner for the time effect.
Example
| Item | Basis | Amount |
|---|---|---|
| Excavation and disposal of 120 square metres | Project Manager's assumption | £36,000 |
| Wet-weather standing time, 40% chance on £8,000 | Risk allowance | £3,200 |
| Fee at an illustrative 10% | On Defined Cost | £3,920 |
| Total change to the Prices | £43,120 |
If the investigation finds 200 square metres, the Project Manager notifies a correction and the extra 80 are assessed. If the weather stays dry, the £3,200 stays, because it priced a risk you carried.
Related guides
- Quotations for compensation events
- Revised quotations: when and why
- Compensation event quotation template and guide
- Notifying a compensation event before it happens
This guide is general information, not legal advice. Check it against your contract.