NEC on tunnelling projects: what to plan for
How NEC contracts meet the realities of tunnelling: ground risk, long linear programmes, shafts, third parties and the pressure points to plan around.
On this page
Tunnelling puts more weight on the ground, and on a few long, linear activities, than almost any other type of work. That shapes how an NEC contract behaves. If you are new to NEC and arriving on a tunnel job, these are the places the contract will be tested.
Why tunnelling changes the programme
A drive is a long chain of near-repeating work with very little room to move. The critical path often runs through shaft construction, machine delivery and assembly, the drive itself, and the lining and fit-out that follow. A slip early in that chain cannot usually be recovered later, so small delays quickly become delays to the Completion Date.
Ground conditions drive the rate of progress, yet the ground is the one thing nobody can see fully in advance. That is why tunnelling contracts lean on the investigation information the Client provides and on how risk for the ground has been allocated.
The NEC pressure points
| Pressure point | What to watch | Where to look |
|---|---|---|
| Ground conditions | Whether the conditions you meet are worse than a competent contractor could reasonably have allowed for from the information provided | Physical conditions explained and unforeseen ground conditions |
| Contaminated or hazardous material | Spoil that cannot be handled or disposed of as planned | Contaminated ground |
| Utilities and obstructions | Services and old structures that are not where the records say | Unmarked utilities found |
| Third parties and consents | Permits, possessions, landowner access and others working at the same shafts | Others delaying you and permits delayed |
| Access to shaft sites | Dates by which working areas are handed over | Access dates |
| Key Dates | Dates for breakthrough, handover of a reception shaft or release of a possession | Key Dates and sectional completion |
Programme habits that help
- Show the drive as a real logic chain, not one long bar. Separate launch, advance by ring or section, cross-passages, breakthrough and recovery, so a stoppage can be shown where it actually happened.
- Make the assumptions visible. Write down the advance rate and the ground conditions your programme assumes. That is what you will compare against when conditions change.
- Hold time risk allowance where the risk sits. An allowance for ground uncertainty belongs next to the drive, clearly labelled, not buried in durations. See float and time risk allowance.
- Protect terminal float. On a long drive the gap between planned Completion and the Completion Date is valuable. See terminal float.
- Give early warnings early. Settlement readings creeping towards a trigger level, a machine that has underperformed for a week, a consent that is slipping: each is an early warning. See what should be early warned.
Questions to ask on day one
- What ground information did the Client provide, and what does the contract say about relying on it?
- Which party carries the risk of the ground under the chosen Option? See risk allocation by Main Option.
- What access dates and Key Dates affect the shafts and reception sites?
- What tests, inspections and monitoring does the Scope require, and what do they cost in time? See tests and inspections.
- Who else will be working in or near the same working areas?
This guide is general information, not legal advice. Check it against your contract.